Engineering Installation > ENGINEERING CASE

The Whole Installation of 800T/D Urea System for Hubei Huaqiang Chemical Group Co. Ltd

Time:2014-6-26


In 2007, our company for 45 days to finish the Hubei Huaqiang chemical 800T/D urea system complete installation, become "Huaqiang" company and China a "miracle"!

Installation scope:

One, equipment installation: the main plant to the six floor and prilling tower spraylayer, including operation of equipment, installation, commissioning qualified transport31 sets; static transport equipment, hoisting, installation of 63 sets, correction;

Two, equipment piping: the main plant building interior point to the six floor area of allpiping installation;

Three, carbon dioxide, water depth, hydrolysis of urea cycle, air compressor station,the main building, the urea prilling tower, Zhanqiao, packaging, in the region of the pipe rack and fire fighting water pipe installation;

Four, inspection, reconstruction;

Five, the two urea tower into a heater: include the installation of the tower, distillationtower, a tail gas absorption tower, a tower, two tower, tail gas absorption tower and other important equipment parts, all piping, equipment, valves, pipe clamp, pipe clampsupport frame, steel pipe homemade and mounting.


Hubei Huaqiang chemical construction site

The synthesis of DN1200mm tower crane

Day and night construction to ensure the project schedule

 Hoisting equipment in place